  * Mosel Example Problems                              *
  * ======================                              *
  *                                                     *
  * file pplan.mos                                      *
  * ``````````````                                      *
  * Example for the use of the Mosel language           *
  * (Manpower planning problem)                         *
  *                                                     *
  * (c) 2008 Fair Isaac Corporation                     *
  *     author: S. Heipcke, 2001, rev. 2003, rev. 2010  *
  *******************************************************!)
model Pplan                      ! Start a new model
uses "mmxprs"                    ! Load the optimizer library
parameters
 USESOS = false                  ! Set to true to use formulation with SOS
end-parameters
declarations
 RProj = 1..3                    ! Range of projects
 NTime = 6                       ! Time horizon
 RTime = 1..NTime                ! Range of months to plan for
 
 DUR: array(RProj) of integer    ! Duration of project p
 RESUSE: array(RProj,RTime) of integer  ! Resource usage of project p in 
                                        ! its t'th month
 RESMAX: array(RTime) of integer ! Resource available in month t
 BEN: array(RProj) of real       ! Benefit per month once project finished
 
 x: array(RProj,RTime) of mpvar  ! 1 if project p starts in month t, else 0
 start: array(RProj) of mpvar    ! Month in which project p starts
end-declarations
 DUR   :: [3, 3, 4]
 RESMAX:: [5, 6, 7, 7, 6, 6]
 BEN   :: [10.2, 12.3, 11.2]
 RESUSE::(1,1..3) [3, 4, 2]
 RESUSE::(2,1..3) [4, 1, 5]
 RESUSE::(3,1..4) [3, 2, 1, 2]      ! Other RESUSE entries are 0 by default
   
! Objective: Maximize Benefit
! If project p starts in month t, it finishes in month t+DUR(p)-1 and 
! contributes a benefit of BEN(p) for the remaining NTime-(t+DUR(p)-1)
! months:  
 MaxBen:= 
  sum(p in RProj,t in 1..NTime-DUR(p)) (BEN(p)*(NTime-t-DUR(p)+1)) * x(p,t)
! Resource availability
! A project starting in month s is in its t-s+1'st month in month t: 
 forall(t in RTime) ResMax(t):=
  sum(p in RProj,s in 1..t) RESUSE(p,t-s+1)*x(p,s) <= 
   RESMAX(t)
! Logical Constraints: Each project starts once and only once:  
 forall(p in RProj) One(p):= sum(t in RTime) x(p,t) = 1.0
 
! Connect variables x(p,t) and start(p)
 forall(p in RProj) Connect(p):= sum(t in RTime) t*x(p,t) = start(p)
! Finish everything by the end of the planning period
 forall(p in RProj) start(p) <= NTime-DUR(p)+1
 
 if not USESOS then              ! Turn variables x into binaries
  forall(p in RProj,t in RTime) x(p,t) is_binary
 else                            ! Define SOS-1 sets that ensure that at 
                                 ! most one x is non-zero for each project p.
                                 ! Use month index order for variables
  forall(p in RProj) XSet(p):= sum(t in RTime) t*x(p,t) is_sos1
 end-if
  
 maximize(MaxBen)                ! Solve the MIP-problem
                                 ! Print out the solution
 writeln("Solution ",if(USESOS,"(using SOS):","(without SOS):"))
 writeln(" Objective: ", getobjval)
 write("   ")
 forall(t in RTime) write(t)
 writeln
 forall(p in RProj) do
  write(p, ": ")
  forall(t in RTime) 
   write( if(t |