task_serialize
task_serialize |
Purpose
Creates a Task Serializer branching scheme that serializes the tasks passed in argument. The branching consists in choosing one task to schedule. Then a branch is created for each possible duration for this task. Once the duration is determined a branch is created for each posssible starting values for this task. When the start and the duration are fixed, the task is scheduled and the process is repeated until all the tasks are serialized.
Synopsis
function task_serialize(taskSelector:string, durationHeuristic:string, startHeuristic:string, tasks:set of cptask) : cpbranching
function task_serialize(taskSelector:string, durationHeuristic:string, startHeuristic:string, tasks:array of cptask) : cpbranching
function task_serialize(taskSelector:string, durationHeuristic:string, startHeuristic:string, tasks:array of cptask, limit:integer) : cpbranching
function task_serialize(taskSelector:string, durationHeuristic:string, startHeuristic:string, tasks:array of cptask, limit:integer) : cpbranching
function task_serialize(taskSelector:string, durationHeuristic:string, startHeuristic:string, tasks:array of cptask, limit:integer) : cpbranching
function task_serialize(taskSelector:string, durationHeuristic:string, startHeuristic:string, tasks:array of cptask, limit:integer) : cpbranching
Arguments
|
taskSelector
|
the task selector
|
|
durationHeuristic
|
the task duration assignment heuristic
|
|
startHeuristic
|
the task start time assignment heuristic
|
|
tasks
|
the set of tasks to be serialized.
|
|
limit
|
discrepancy limit: value 0 means strictly following the branching scheme, positive values indicate the permissible number of deviations from the branching scheme.
|
Return value
The resulting Task Serializer branching scheme
Example
The following example shows how to use the task_serialize branching scheme to solve a small cumulative scheduling problem:
*****************************************************************!)
model "Tasks serialization example"
uses "kalis"
declarations
Masonry, Carpentry, Roofing, Windows, Facade, Garden, Plumbing,
Ceiling, Painting, MovingIn : cptask ! Declaration of tasks
taskset : set of cptask
money_available : cpresource ! Resource declaration
end-declarations
forward function selectNextTask(tasks: cptasklist) : integer
! 'money_available' is a cumulative resource with max. amount of 29$
set_resource_attributes(money_available,KALIS_DISCRETE_RESOURCE,29)
! Limit resource availability to 20$ in the time interval [0,14]
setcapacity( money_available, 0, 14, 20 )
! Setting the task durations and predecessor sets
set_task_attributes(Masonry , 7 )
set_task_attributes(Carpentry, 3, {Masonry} )
set_task_attributes(Roofing , 1, {Carpentry} )
set_task_attributes(Windows , 1, {Roofing} )
set_task_attributes(Facade , 2, {Roofing} )
set_task_attributes(Garden , 1, {Roofing} )
set_task_attributes(Plumbing , 8, {Masonry} )
set_task_attributes(Ceiling , 3, {Masonry} )
set_task_attributes(Painting , 2, {Ceiling} )
set_task_attributes(MovingIn , 1, {Windows,Facade,Garden,Painting})
! Setting the resource consumptions
consumes(Masonry , 7, money_available )
consumes(Carpentry, 3, money_available )
consumes(Roofing , 1, money_available )
consumes(Windows , 1, money_available )
consumes(Facade , 2, money_available )
consumes(Garden , 1, money_available )
consumes(Plumbing , 8, money_available )
consumes(Ceiling , 3, money_available )
consumes(Painting , 2, money_available )
consumes(MovingIn , 1, money_available )
! Set of tasks to schedule
taskset := {Masonry, Carpentry, Roofing, Windows, Facade, Garden,
Plumbing, Ceiling, Painting, MovingIn}
! Set the custom branching strategy using task_serialize:
! - the task serialization process will use the function
! "selectNextTask" to look for the next task to fix
! - it will use the "KALIS_MAX_TO_MIN" value selection heuristic
! to set the tasks duration variable
! - and the "KALIS_MIN_TO_MAX" value selection heuristic to set
! the start of the task
cp_set_branching(task_serialize("selectNextTask",
KALIS_MAX_TO_MIN, KALIS_MIN_TO_MAX, taskset))
! Find the optimal schedule (minimizing the makespan)
if (0 <> cp_schedule(getmakespan)) then
cp_show_sol
else
writeln("No solution found")
end-if
!-------------------------------------------------------------
! **** Function to select the next task to schedule
function selectNextTask(tasks: cptasklist) : integer
write("selectNextTask : ")
declarations
Vset,Iset: set of integer
end-declarations
! Get the number of elements of "tasks"
listsize:= getsize(tasks)
! Set of uninstantiated variables
forall(i in 1..listsize)
if not is_fixed(getstart(gettask(tasks,i))) or
not is_fixed(getduration(gettask(tasks,i))) then
Vset+= {i};
end-if
if Vset={} then
returned:= 0
else
! Get the variables with max. degree
dmax:= max(i in Vset) getsize(getduration(gettask(tasks,i)))
forall(i in Vset)
if getsize(getduration(gettask(tasks,i))) = dmax then
Iset+= {i}; end-if
dsize:= MAX_INT
! Choose var. with smallest domain among those indexed by 'Iset'
forall(i in Iset)
if getsize(getstart(gettask(tasks,i))) < dsize then
returned:= i
dsize:= getsize(getstart(gettask(tasks,i)))
end-if
end-if
if (returned <> 0) then
writeln(gettask(tasks,returned))
end-if
end-function
end-model
Related topics