Example: Machine assignment and sequencing

We need to produce 12 products on a set of three machines. Each machine may produce all of the products but processing times and costs vary (Table Machine-dependent production costs and durations). Furthermore, for every product we are given its release and due dates (Table Release dates and due dates of products). We wish to determine a production plan for all products that minimizes the total production cost.

Table 2: Machine-dependent production costs and durations
Production costs   Durations
Prod. \ Mach. 1 2 3 1 2 3
1   12 6 7   10 14 13
2 13 6 10 7 9 8
3 10 4 6 11 17 15
4 8 4 5 6 9 12
5 12 6 7 4 6 10
6 10 5 6 2 3 4
7 7 4 5 10 15 16
8 9 5 5 8 11 12
9 10 5 7 10 14 13
10 8 4 5 8 11 14
11 15 8 9 9 12 16
12 13 7 7 3 5 6

Table 3: Release dates and due dates of products
Product 1 2 3 4 5 6 7 8 9 10 11 12
Release 2 4 5 7 9 0 3 6 11 2 3 4
Due date  32 33 36 37 39 34 30 26 36 38 31 22