Integer Programming


Type: Resource-constrained project scheduling
Rating: 3 (intermediate)
Description: Alternative formulations using either binary variables (pplan.mos) or SOS-1 (pplan2.mos)
File(s): pplan.mos, pplan2.mos

pplan.mos
(!******************************************************
   Mosel User Guide Example Problems
   ================================= 

   file pplan.mos
   ``````````````
   Manpower planning: MIP example.
   
   (c) 2008 Fair Isaac Corporation
       author: S. Heipcke, 2001, rev. Sep. 2013
*******************************************************!)

model Pplan 
 uses "mmxprs"

 declarations
  PROJ = 1..3                      ! Set of projects
  NM = 6                           ! Time horizon (months)
  MONTHS = 1..NM                   ! Set of time periods (months) to plan for
 
  DUR: array(PROJ) of integer      ! Duration of project p
  RESUSE: array(PROJ,MONTHS) of integer 
                                   ! Res. usage of proj. p in its t'th month
  RESMAX: array(MONTHS) of integer ! Resource available in month m
  BEN: array(PROJ) of real         ! Benefit per month once project finished
 
  start: array(PROJ,MONTHS) of mpvar  ! 1 if proj p starts in month t, else 0
 end-declarations

 DUR   :: [3, 3, 4]
 RESMAX:: [5, 6, 7, 7, 6, 6]
 BEN   :: [10.2, 12.3, 11.2]
 RESUSE:: (1,1..3)[3, 4, 2]
 RESUSE:: (2,1..3)[4, 1, 5]
 RESUSE:: (3,1..4)[3, 2, 1, 2]     ! Other RESUSE entries are 0 by default

! Objective: Maximize Benefit
! If project p starts in month t, it finishes in month t+DUR(p)-1 and 
! contributes a benefit of BEN(p) for the remaining NM-(t+DUR(p)-1) months:
 MaxBen:= 
  sum(p in PROJ, m in 1..NM-DUR(p)) (BEN(p)*(NM-m-DUR(p)+1)) * start(p,m)

! Each project starts once and only once:  
 forall(p in PROJ) One(p):= sum(m in MONTHS) start(p,m) = 1

! Resource availability
! A project starting in month m is in its k-m+1'st month in month k: 
 forall(k in MONTHS) ResMax(k):=
  sum(p in PROJ, m in 1..k) RESUSE(p,k+1-m)*start(p,m) <= RESMAX(k)

! Make all the start variables binary
 forall(p in PROJ, m in MONTHS) start(p,m) is_binary

 maximize(MaxBen)                   ! Solve the MIP-problem

 writeln("Solution value is: ", getobjval)
 forall(p in PROJ) writeln( p, " starts in month ", 
                            getsol(sum(m in 1..NM-DUR(p)) m*start(p,m)) )
end-model

pplan2.mos
(!******************************************************
   Mosel User Guide Example Problems
   ================================= 

   file pplan2.mos
   ```````````````
   Defining SOS1.
   
   (c) 2008 Fair Isaac Corporation
       author: S. Heipcke, 2001, rev. Sep. 2013
*******************************************************!)

model Pplan2 
 uses "mmxprs"

 declarations
  PROJ = 1..3                      ! Set of projects
  NM = 6                           ! Time horizon (months)
  MONTHS = 1..NM                   ! Set of time periods (months) to plan for
 
  DUR: array(PROJ) of integer      ! Duration of project p
  RESUSE: array(PROJ,MONTHS) of integer 
                                   ! Res. usage of proj. p in its t'th month
  RESMAX: array(MONTHS) of integer ! Resource available in month m
  BEN: array(PROJ) of real         ! Benefit per month once project finished
 
  start: array(PROJ,MONTHS) of mpvar  ! 1 if proj p starts in month t, else 0
 end-declarations

 DUR   :: [3, 3, 4]
 RESMAX:: [5, 6, 7, 7, 6, 6]
 BEN   :: [10.2, 12.3, 11.2]
 RESUSE:: (1,1..3)[3, 4, 2]
 RESUSE:: (2,1..3)[4, 1, 5]
 RESUSE:: (3,1..4)[3, 2, 1, 2]     ! Other RESUSE entries are 0 by default

! Objective: Maximize Benefit
! If project p starts in month t, it finishes in month t+DUR(p)-1 and 
! contributes a benefit of BEN(p) for the remaining NM-(t+DUR(p)-1) months:
 MaxBen:= 
  sum(p in PROJ, m in 1..NM-DUR(p)) (BEN(p)*(NM-m-DUR(p)+1)) * start(p,m)

! Each project starts once and only once:  
 forall(p in PROJ) One(p):= sum(m in MONTHS) start(p,m) = 1

! Resource availability:
! A project starting in month m is in its k-m+1'st month in month k: 
 forall(k in MONTHS) ResMax(k):=
  sum(p in PROJ, m in 1..k) RESUSE(p,k+1-m)*start(p,m) <= RESMAX(k)

! Define SOS-1 sets that ensure that at most one start(p,m) is non-zero
! for each project p. Use month index to order the variables
 forall(p in PROJ) XSet(p):= sum(m in MONTHS) m*start(p,m) is_sos1

 maximize(MaxBen)                   ! Solve the MIP-problem

 writeln("Solution value is: ", getobjval)
 forall(p in PROJ) writeln( p, " starts in month ", 
                            getsol(sum(m in 1..NM-DUR(p)) m*start(p,m)) )
end-model

© 2001-2019 Fair Isaac Corporation. All rights reserved. This documentation is the property of Fair Isaac Corporation (“FICO”). Receipt or possession of this documentation does not convey rights to disclose, reproduce, make derivative works, use, or allow others to use it except solely for internal evaluation purposes to determine whether to purchase a license to the software described in this documentation, or as otherwise set forth in a written software license agreement between you and FICO (or a FICO affiliate). Use of this documentation and the software described in it must conform strictly to the foregoing permitted uses, and no other use is permitted.