Example: Machine assignment and sequencing

We need to produce 12 products on a set of three machines. Each machine may produce all of the products but processing times and costs vary (Table Machine-dependent production costs and durations). Furthermore, for every product we are given its release and due dates (Table Release dates and due dates of products). We wish to determine a production plan for all products that minimizes the total production cost.

Table 2: Machine-dependent production costs and durations
Production costs   Durations
Prod. \ Mach. 1 2 3 1 2 3
1   12 6 7   10 14 13
2 13 6 10 7 9 8
3 10 4 6 11 17 15
4 8 4 5 6 9 12
5 12 6 7 4 6 10
6 10 5 6 2 3 4
7 7 4 5 10 15 16
8 9 5 5 8 11 12
9 10 5 7 10 14 13
10 8 4 5 8 11 14
11 15 8 9 9 12 16
12 13 7 7 3 5 6

Table 3: Release dates and due dates of products
Product 1 2 3 4 5 6 7 8 9 10 11 12
Release 2 4 5 7 9 0 3 6 11 2 3 4
Due date  32 33 36 37 39 34 30 26 36 38 31 22

© 2001-2019 Fair Isaac Corporation. All rights reserved. This documentation is the property of Fair Isaac Corporation (“FICO”). Receipt or possession of this documentation does not convey rights to disclose, reproduce, make derivative works, use, or allow others to use it except solely for internal evaluation purposes to determine whether to purchase a license to the software described in this documentation, or as otherwise set forth in a written software license agreement between you and FICO (or a FICO affiliate). Use of this documentation and the software described in it must conform strictly to the foregoing permitted uses, and no other use is permitted.