getproduction

getproduction


Purpose
Gets the cpvar representing the production of a task for a particular resource.
A task produces some amount of processing power for a resource at its start. The capacity produced is considered as non-renewable which means that the produced capacity remains available even after the termination of the task.
Synopsis
function getproduction(task:cptask, resource:cpresource) : cpvar
function getproduction(task:cptask, resource:cpresource, p:integer) : integer
Arguments
task 
the task
resource 
the resource
the timestep
Return value
The cpvar representing the production of 'resource' by 'task'
Example
The following example illustrates this:
Scheduling/ProducerConsumer.png
model "Producer Consumer"
 uses "kalis"

 declarations
  Masonry, Carpentry, Roofing, Windows, Facade, Garden, Plumbing,
    Ceiling, Painting, MovingIn : cptask    ! Declaration of tasks
  money_available : cpresource              ! Resource declaration
 end-declarations

! 'money_available' is a cumulative resource with max. amount of 29$
 set_resource_attributes(money_available,KALIS_DISCRETE_RESOURCE,29)

! Limit resource availability to 20$ in the time interval [0,14]
 setcapacity(money_available, 0, 14, 20)

! Setting the task durations and predecessor sets
 set_task_attributes(Masonry  , 7 )
 set_task_attributes(Carpentry, 3, {Masonry} )
 set_task_attributes(Roofing  , 1, {Carpentry} )
 set_task_attributes(Windows  , 1, {Roofing} )
 set_task_attributes(Facade   , 2, {Roofing} )
 set_task_attributes(Garden   , 1, {Roofing} )
 set_task_attributes(Plumbing , 8, {Masonry} )
 set_task_attributes(Ceiling  , 3, {Masonry} )
 set_task_attributes(Painting , 2, {Ceiling} )
 set_task_attributes(MovingIn , 1, {Windows,Facade,Garden,Painting})

! Setting the resource consumptions
 consumes(Masonry  , 7, money_available )
 consumes(Carpentry, 3, money_available )
 consumes(Roofing  , 1, money_available )
 consumes(Windows  , 1, money_available )
 consumes(Facade   , 2, money_available )
 consumes(Garden   , 1, money_available )
 consumes(Plumbing , 8, money_available )
 consumes(Ceiling  , 3, money_available )
 consumes(Painting , 2, money_available )
 consumes(MovingIn , 1, money_available )

! Find the optimal schedule (minimizing the makespan)
 if cp_minimize(getmakespan) then	
   cp_show_sol		
 else
   writeln("No solution found")
 end-if

end-model

Related topics

© 2001-2019 Fair Isaac Corporation. All rights reserved. This documentation is the property of Fair Isaac Corporation (“FICO”). Receipt or possession of this documentation does not convey rights to disclose, reproduce, make derivative works, use, or allow others to use it except solely for internal evaluation purposes to determine whether to purchase a license to the software described in this documentation, or as otherwise set forth in a written software license agreement between you and FICO (or a FICO affiliate). Use of this documentation and the software described in it must conform strictly to the foregoing permitted uses, and no other use is permitted.