Planning of paint production


Type: Producion planning
Rating:
Description: Planning of paint production:
  • linear, 'element', 'implies', and 'all-different' constraints (b5paint_ka.mos).
  • Alternative formulation using 'disjunctive' and 2-dimensional 'element' constraints (b5paint2_ka.mos).
  • Third model version (b5paint3_ka.mos) using 'cycle' constraint.
  • Forth model formulation (b5paint4_ka.mos) as disjunctive scheduling problem with setup times, modeled with task and resource objects, using 'equiv', 'element', 'maximum' constraints and defining an enumeration strategy based on tasks and variables.
File(s): b5paint_ka.mos, b5paint2_ka.mos, b5paint3_ka.mos, b5paint4_ka.mos
Data file(s): b5paint.dat


b5paint_ka.mos
(!******************************************************
   CP Example Problems
   ===================

   file b5paint_ka.mos
   ```````````````````
   Planning of paint production
   (See "Applications of optimization with Xpress-MP",
        Section 7.5 Paint production)

   *** This model cannot be run with a Community Licence 
       for the provided data instance ***

   (c) 2008 Artelys S.A. and Fair Isaac Corporation
       
*******************************************************!)

model "B-5 Paint production (CP)"
 uses "kalis"

 declarations
  NJ = 5                             ! Number of paint batches (=jobs)
  JOBS=1..NJ

  DUR: array(JOBS) of integer        ! Durations of jobs
  CLEAN: array(JOBS,JOBS) of integer ! Cleaning times between jobs
  CB: array(JOBS) of integer         ! Cleaning times after a batch

  succ: array(JOBS) of cpvar         ! Successor of a batch
  clean: array(JOBS) of cpvar        ! Cleaning time after batches
  y: array(JOBS) of cpvar            ! Variables for excluding subtours
  cycleTime: cpvar                   ! Objective variable
 end-declarations

 initializations from 'Data/b5paint.dat'
  DUR CLEAN 
 end-initializations
 
 forall(j in JOBS) do
  1 <= succ(j); succ(j) <= NJ; succ(j) <> j
  1 <= y(j); y(j) <= NJ
 end-do

! Cleaning time after every batch
 forall(j in JOBS) do
  forall(i in JOBS) CB(i):= CLEAN(j,i)
  clean(j) = element(CB, succ(j))
 end-do 
 
! Objective: minimize the duration of a production cycle
 cycleTime = sum(j in JOBS) (DUR(j)+clean(j))

! One successor and one predecessor per batch
 all_different(succ)

! Exclude subtours
 forall(i in JOBS, j in 2..NJ | i<>j) 
  implies(succ(i) = j, y(j) = y(i) + 1)

! Solve the problem
 if not cp_minimize(cycleTime) then
  writeln("Problem is infeasible")
  exit(1)
 end-if
 cp_show_stats

! Solution printing
 writeln("Minimum cycle time: ", getsol(cycleTime))
 writeln("Sequence of batches:\nBatch Duration Cleaning")
 first:=1 
 repeat
  writeln("  ", first, strfmt(DUR(first),8), strfmt(getsol(clean(first)),9))
  first:=getsol(succ(first))
 until (first=1)

end-model

b5paint2_ka.mos
(!******************************************************
   CP Example Problems
   ===================

   file b5paint2_ka.mos
   ```````````````````
   Planning of paint production
   (See "Applications of optimization with Xpress-MP",
        Section 7.5 Paint production)
   - Alternative formulation using disjunctions and 
     2D element constraints -
   
   (c) 2008 Artelys S.A. and Fair Isaac Corporation
       
*******************************************************!)

model "B-5 Paint production (CP)"
 uses "kalis"

 declarations   
  NJ = 5                             ! Number of paint batches (=jobs)
  JOBS=1..NJ

  DUR: array(JOBS) of integer        ! Durations of jobs
  CLEAN: array(JOBS,JOBS) of integer ! Cleaning times between jobs

  rank: array(JOBS) of cpvar         ! Number of job in position k
  clean: array(JOBS) of cpvar        ! Cleaning time after batches
  cycleTime: cpvar                   ! Objective variable
 end-declarations

 initializations from 'Data/b5paint.dat'
  DUR CLEAN 
 end-initializations
 
 forall(k in JOBS) setdomain(rank(k), JOBS) 

! Cleaning time after every batch
 forall(k in JOBS)
  if k<NJ then
   element(CLEAN, rank(k), rank(k+1)) = clean(k)
  else
   element(CLEAN, rank(k), rank(1)) = clean(k)
  end-if
 
! Objective: minimize the duration of a production cycle
 cycleTime = sum(j in JOBS) DUR(j) + sum(k in JOBS) clean(k)

! One position for every job
 all_different(rank)

! Solve the problem
 if not cp_minimize(cycleTime) then
  writeln("Problem is infeasible")
  exit(1)
 end-if
 cp_show_stats

! Solution printing
 writeln("Minimum cycle time: ", getsol(cycleTime))
 writeln("Sequence of batches:\nBatch Duration Cleaning")
 forall(k in JOBS)
  writeln("  ", getsol(rank(k)), strfmt(DUR(getsol(rank(k))),8), 
          strfmt(getsol(clean(k)),9))

end-model

b5paint3_ka.mos
(!******************************************************
   CP Example Problems
   ===================

   file b5paint3_ka.mos
   ````````````````````
   Planning of paint production
   (See "Applications of optimization with Xpress-MP",
        Section 7.5 Paint production)
   - Formulation using 'cycle' constraint -

   (c) 2008 Artelys S.A. and Fair Isaac Corporation
       Creation: 2006, rev. Mar. 2013              
*******************************************************!)

model "B-5 Paint production (CP)"
 uses "kalis"

 setparam("KALIS_DEFAULT_LB", 0)

 declarations
  NJ = 5                             ! Number of paint batches (=jobs)
  JOBS=0..NJ-1

  DUR: array(JOBS) of integer        ! Durations of jobs
  CLEAN: array(JOBS,JOBS) of integer ! Cleaning times between jobs
  CB: array(JOBS) of integer         ! Cleaning times after a batch

  succ: array(JOBS) of cpvar         ! Successor of a batch
  cleanTime,cycleTime: cpvar         ! Durations of cleaning / complete cycle
 end-declarations

 initializations from 'Data/b5paint.dat'
  DUR CLEAN 
 end-initializations
 
 forall(j in JOBS) do
  0 <= succ(j); succ(j) <= NJ-1; succ(j) <> j
 end-do

! Assign values to 'succ' variables as to obtain a single cycle
! 'cleanTime' is the sum of the cleaning times
 cycle(succ, cleanTime, CLEAN)
 
! Objective: minimize the duration of a production cycle
 cycleTime = cleanTime +sum(j in JOBS) DUR(j)

! Solve the problem
 if not cp_minimize(cycleTime) then
  writeln("Problem is infeasible")
  exit(1)
 end-if
 cp_show_stats

! Solution printing
 writeln("Minimum cycle time: ", getsol(cycleTime))
 writeln("Sequence of batches:\nBatch Duration Cleaning")
 first:=1 
 repeat
  writeln("  ", first, strfmt(DUR(first),8),
                strfmt(CLEAN(first,getsol(succ(first))),9) )
  first:=getsol(succ(first))
 until (first=1)

end-model

b5paint4_ka.mos
(!******************************************************
   Mosel Example Problems
   ======================

   file b5paint4_ka.mos
   ```````````````````
   Planning of paint production
   - Alternative formulation using disjunctions  
     between tasks -
   
   *** This model cannot be run with a Community Licence 
       for the provided data instance ***

   (c) 2008 Artelys S.A. and Fair Isaac Corporation
       
*******************************************************!)

model "B-5 Paint production (CP)"
 uses "kalis"
 
 declarations   
  NJ = 5                             ! Number of paint batches (=jobs)
  JOBS=1..NJ

  DUR: array(JOBS) of integer        ! Durations of jobs
  CLEAN: array(JOBS,JOBS) of integer ! Cleaning times between jobs

  task: array(JOBS) of cptask
  res: cpresource

  firstjob,lastjob,cleanlf,finish: cpvar
  L: cpvarlist
  cycleTime: cpvar                   ! Objective variable
  Strategy: array(range) of cpbranching
 end-declarations

 initializations from 'Data/b5paint.dat'
  DUR CLEAN 
 end-initializations
 
! Setting up the resource (formulation of the disjunction of tasks)
 set_resource_attributes(res, KALIS_UNARY_RESOURCE, 1)
  
! Setting up the tasks 
 forall(j in JOBS) getstart(task(j)) >= 1                     ! Start times
 forall(j in JOBS) set_task_attributes(task(j), DUR(j), res)  ! Dur.s + disj.
 forall(j,k in JOBS) setsetuptime(task(j), task(k), CLEAN(j,k), CLEAN(k,j)) 
                                     ! Cleaning times between batches

! Cleaning time at end of cycle (between last and first jobs)
 setdomain(firstjob, JOBS); setdomain(lastjob, JOBS)
 firstjob <> lastjob
 forall(j in JOBS) equiv(getend(task(j))=getmakespan, lastjob=j)
 forall(j in JOBS) equiv(getstart(task(j))=1, firstjob=j)
 cleanlf = element(CLEAN, lastjob, firstjob)

 forall(j in JOBS) L += getend(task(j))
 finish = maximum(L)

! Objective: minimize the duration of a production cycle
 cycleTime = finish - 1 + cleanlf
  
! Solve the problem
 if cp_schedule(cycleTime) = 0 then
  writeln("Problem is infeasible")
  exit(1)
 end-if
 cp_show_stats

! Solution printing
 declarations
  SUCC: array(JOBS) of integer
 end-declarations

 forall(j in JOBS)
  forall(k in JOBS)
   if getsol(getstart(task(k))) = getsol(getend(task(j)))+CLEAN(j,k) then
    SUCC(j):= k
    break
   end-if 
 writeln("Minimum cycle time: ", getsol(cycleTime))
 writeln("Sequence of batches:\nBatch Start Duration Cleaning")
 forall(k in JOBS)
  writeln("  ", k, strfmt(getsol(getstart(task(k))),7), strfmt(DUR((k)),8), 
          strfmt(if(SUCC(k)>0, CLEAN(k,SUCC(k)), getsol(cleanlf)),9))

end-model

© 2001-2020 Fair Isaac Corporation. All rights reserved. This documentation is the property of Fair Isaac Corporation (“FICO”). Receipt or possession of this documentation does not convey rights to disclose, reproduce, make derivative works, use, or allow others to use it except solely for internal evaluation purposes to determine whether to purchase a license to the software described in this documentation, or as otherwise set forth in a written software license agreement between you and FICO (or a FICO affiliate). Use of this documentation and the software described in it must conform strictly to the foregoing permitted uses, and no other use is permitted.