table_constraint
table_constraint |
function table_constraint(vars:array of cpvar, tuple:array) : cpctr
function table_constraint(vars:array of cpvar, tuple:set) : cpctr
function table_constraint(vars:cpvarlist, tuple:array) : cpctr
function table_constraint(vars:cpvarlist, tuple:set) : cpctr
|
vars
|
an array or cpvarlist of decision variables
|
|
tuple
|
the list of valid tuples for the decision variables
|
model "table_constraint example"
uses "kalis"
parameters
N = 30 ! Max number of bins
MAX_TIME = 15 ! Max time allowed to solver
end-parameters
setparam("KALIS_MAX_COMPUTATION_TIME",MAX_TIME)
forward procedure print_sol
declarations
! *** Data ***
MATERIAL = 1..5 ! Corresponds to ["Glass","Plastic","Steel","Wood","Copper"]
INITIAL_SUPPLY : array(MATERIAL) of integer
BINTYPE = 0..3 ! Corresponds to ["Unassigned", "Red", "Blue", "Green"]
BINS = 1..N ! Set of bins
CAPACITY : array(BINTYPE) of integer ! Capacity per type
WEIGHT : array(BINTYPE) of integer ! Weights for bin type selection
! *** Decision variables ***
var_bin : array(BINS) of cpvar ! Bin usage
var_type : array(BINS) of cpvar ! Bin type
var_capa : array(BINS) of cpvar ! Bin capacity
var_qty_material : array(BINS,MATERIAL) of cpvar ! Qty per material in bins
objective : cpvar
strategy : cpbranching ! Branching strategy
! Configuration of the table_constraint
var_table : array(BINS) of cpvarlist ! Assignment variables per bin
list_valid_tuple : set of list of integer ! Permissible tuples
end-declarations
! Initialisation of the data arrays
INITIAL_SUPPLY::(1..5)[12,10,8,12,8]
CAPACITY::(0..3)[0,5,5,6]
WEIGHT::(0..3)[0,1,1,1]
! Define the cpvar and their domains
forall(i in BINS) do
setname(var_bin(i), "use of bin (" + i + ")")
setdomain(var_bin(i),0,1)
setname(var_type(i), "type of bin (" + i + ")")
setdomain(var_type(i),BINTYPE)
setname(var_capa(i), "capacity of bin (" + i + ")")
var_capa(i) = element(CAPACITY,var_type(i))
forall(m in MATERIAL) do
setname(var_qty_material(i,m),
"Quantity of material (" + m + ") in bin (" + i + ")")
setdomain(var_qty_material(i,m),0,max(c in BINTYPE) CAPACITY(c))
end-do
end-do
! Capacity constraint
forall(i in BINS) do
sum(m in MATERIAL) var_qty_material(i,m) <= var_capa(i)
var_bin(i) = element(WEIGHT,var_type(i))
end-do
! Satisfy of the supply constraint
forall(m in MATERIAL)
sum(i in BINS) var_qty_material(i,m) = INITIAL_SUPPLY(m)
! Define a list of valid tuples
maxcap:= max(c in BINTYPE) CAPACITY(c)
forall(type in BINTYPE, qmat_1,qmat_2,qmat_3,
qmat_4,qmat_5 in 0..maxcap) do
! red can contain glass, cooper, wood and at most 1 wood component
if type = 1 and
qmat_2 = 0 and qmat_3 = 0 and qmat_4 <= 1 then
list_valid_tuple += {[type, qmat_1, qmat_2,qmat_3,qmat_4,qmat_5]}
! blue can contain glass, steel, cooper
elif type = 2 and qmat_2 = 0 and qmat_4 = 0 then
list_valid_tuple += {[type, qmat_1, qmat_2,qmat_3,qmat_4,qmat_5]}
! green can contain plastic, copper, wood and at most 2 wood components
elif type = 3 and
qmat_1 = 0 and qmat_3 = 0 and qmat_4 <= 2 then
list_valid_tuple += {[type, qmat_1, qmat_2,qmat_3,qmat_4,qmat_5]}
! unassigned
elif type = 0 and
qmat_1 = 0 and qmat_2 = 0 and qmat_3 = 0 and qmat_4 = 0 and qmat_5 = 0 then
list_valid_tuple += {[type, qmat_1, qmat_2,qmat_3,qmat_4,qmat_5]}
end-if
! wood requires plastic;
if qmat_4 >= 1 and qmat_2 >= 1 then
list_valid_tuple += {[type, qmat_1, qmat_2,qmat_3,qmat_4,qmat_5]}
end-if
! glass exclusive with copper;
if qmat_1 = 0 or qmat_5 = 0 then
list_valid_tuple += {[type, qmat_1, qmat_2,qmat_3,qmat_4,qmat_5]}
end-if
! copper excludes plastic.
if qmat_5 = 0 or qmat_2 = 0 then
list_valid_tuple += {[type, qmat_1, qmat_2,qmat_3,qmat_4,qmat_5]}
end-if
end-do
! Definition of table constraint
forall(i in BINS) do
var_table(i) += var_type(i)
forall(m in MATERIAL) var_table(i) += var_qty_material(i,m);
table_constraint(var_table(i), list_valid_tuple)
end-do
! Define the objective
setname(objective,"total number of bins")
setdomain(objective,0,N)
objective = sum(i in BINS) var_bin(i)
! Propagate the constraints
if not cp_propagate then
writeln("Problem is infeasible")
exit(1)
end-if
! Define a branching strategy
strategy := assign_var(KALIS_MAX_DEGREE,KALIS_MAX_TO_MIN)
cp_set_branching(strategy)
! And solve the problem
if not cp_minimize(objective) then
writeln("Problem is infeasible")
exit(1)
end-if
! Display solution and solver stats
print_sol
cp_show_stats
! **** Solution display ****
procedure print_sol
forall(i in BINS | getsol(var_type(i)) > 0) do
writeln("Bin ",i, " chosen : type=", getsol(var_type(i)),
"; capa=", getsol(var_capa(i)),
"; Glass=", getsol(var_qty_material(i,1)),
"; Plastic=", getsol(var_qty_material(i,2)),
"; Steel=", getsol(var_qty_material(i,3)),
"; Wood=", getsol(var_qty_material(i,4)),
"; Copper=", getsol(var_qty_material(i,5)))
end-do
end-procedure
end-model
© 2001-2020 Fair Isaac Corporation. All rights reserved. This documentation is the property of Fair Isaac Corporation (“FICO”). Receipt or possession of this documentation does not convey rights to disclose, reproduce, make derivative works, use, or allow others to use it except solely for internal evaluation purposes to determine whether to purchase a license to the software described in this documentation, or as otherwise set forth in a written software license agreement between you and FICO (or a FICO affiliate). Use of this documentation and the software described in it must conform strictly to the foregoing permitted uses, and no other use is permitted.