Mosel Example Problems
======================
file jobshopas.mos
``````````````````
Job shop production planning,
second, generic formulation.
(c) 2012 Fair Isaac Corporation
author: S. Heipcke, Sep. 2012, rev. Apr. 2020
*******************************************************!)
model "B-3 Job shop (2)"
uses "mmxprs", "mmsystem"
parameters
DATAFILE = "mt10.dat" ! mt06.dat : Fisher and Thompson 6x6 instance
ALG = 1 ! 0: Default solving, 1: Add partial solution,
! 2: Augment Jobshop problem with one sequencing problem
end-parameters
declarations
NBJOBS: integer ! Number of jobs
NBRES: integer ! Number of resources
end-declarations
initializations from DATAFILE
NBJOBS NBRES
end-initializations
declarations
JOBS = 1..NBJOBS ! Set of jobs
TASKS = 1..NBRES ! Set of tasks (one per machine)
TASKSM1 = 1..NBRES-1 ! Set of tasks without last
RESOURCES = 0..NBRES-1 ! Set of resources
taskUse: array(JOBS,TASKS) of integer ! Resource use of tasks
DUR: array(JOBS,TASKS) of integer ! Durations of tasks
RESIND: array(RESOURCES,JOBS) of integer ! Task index per resource
BIGM: integer
MAXDUR: array(RESOURCES) of integer
cutoff: real
bbindex: integer
end-declarations
initializations from DATAFILE
taskUse DUR as "taskDuration"
end-initializations
forall(m in RESOURCES,j in JOBS,t in TASKS | taskUse(j,t) = m) RESIND(m,j):=t
BIGM:=sum(j in JOBS,t in TASKS) DUR(j,t) ! Some (sufficiently) large value
forall(m in RESOURCES) MAXDUR(m):=sum(j in JOBS) DUR(j,RESIND(m,j))
declarations
start: array(JOBS,TASKS) of mpvar ! Start times of tasks
comp: array(JOBS,TASKS) of mpvar ! Completion times of tasks
makespan: mpvar ! Schedule completion time
y: dynamic array(RESOURCES,JOBS,JOBS) of mpvar ! Disjunction variables
heursol: dynamic array(set of mpvar) of real
rank: array(JOBS,JOBS) of mpvar ! =1 if job j at position k
jcomp,tstart: array(JOBS) of mpvar ! Start time of job at position k
SeqProblem: mpproblem
pos: array(JOBS) of integer
end-declarations
! **** Create disjunctive constraints ****
procedure disjunctiveconstraints(m:integer)
forall(i,j in JOBS | i<j) do
create(y(m,i,j))
y(m,i,j) is_binary !=1 if i>>j, =0 if i<<j
start(i,RESIND(m,i))+DUR(i,RESIND(m,i)) <=
start(j,RESIND(m,j))+BIGM*y(m,i,j)
start(j,RESIND(m,j))+DUR(j,RESIND(m,j)) <=
start(i,RESIND(m,i))+BIGM*(1-y(m,i,j))
end-do
end-procedure
! **** Single machine sequencing problem ****
procedure sequencemachine(m:integer)
! One job per position
forall(k in JOBS) sum(j in JOBS) rank(j,k) = 1
! One position per job
forall(j in JOBS) sum(k in JOBS) rank(j,k) = 1
! Sequence of jobs
forall(k in 1..NBJOBS-1)
tstart(k+1) >=
tstart(k) + sum(j in JOBS) DUR(j,RESIND(m,j))*rank(j,k)
! Start times (release date = min total duration for preceding tasks)
forall(j in JOBS) REL(j):= sum(t in 1..RESIND(m,j)-1) DUR(j,t)
forall(j in JOBS) DURSUCC(j):= sum(t in RESIND(m,j)+1..NBRES) DUR(j,t)
forall(k in JOBS) tstart(k) >= sum(j in JOBS) REL(j)*rank(j,k)
! Completion times
forall(k in JOBS) jcomp(k) =
tstart(k) + sum(j in JOBS) (DUR(j,RESIND(m,j))+DURSUCC(j))*rank(j,k)
forall(j,k in JOBS) rank(j,k) is_binary
! Objective function: minimize latest completion time
forall(k in JOBS) makespan >= jcomp(k)
end-procedure
! **** Status of loaded solutions ****
public procedure solnotify(id:string, status:integer)
writeln_("Optimiser loaded solution ",id," status=",status)
end-procedure
! **** Main problem: Job-shop scheduling problem ****
! Precedence constraints between last task of every job and makespan
forall(j in JOBS) makespan >= start(j,NBRES) + DUR(j,NBRES)
! Precedence constraints between the tasks of every job
forall(j in JOBS,t in TASKSM1)
start(j,t) + DUR(j,t) <= start(j,t+1)
! Disjunctions
forall(r in RESOURCES) disjunctiveconstraints(r)
! Linking start and completion times
forall(j in JOBS,t in TASKS) start(j,t)+DUR(j,t) = comp(j,t)
! Bound on latest completion time
makespan <= BIGM
starttime:=gettime
if ALG>0 then
! Solve the single machine sequencing problems
setparam("XPRS_VERBOSE", false)
forall(m in RESOURCES) do
with SeqProblem do
sequencemachine(m) ! Formulate the problem
minimize(makespan) ! Solve the problem
if getobjval>cutoff then
cutoff:= getobjval;
bbindex:=m
end-if
writeln_("*** (", gettime-starttime, "s) Machine ", m, ": ", getobjval)
forall(j in JOBS) pos(j):= round(sum(k in JOBS) k*rank(j,k).sol)
end-do
forall(i,j in JOBS | i<j ) heursol(y(m,i,j)):= if(pos(i)<pos(j), 0, 1)
loadprob(makespan) ! Make sure problem is loaded
if ALG=1 then
id:="mach"+m
addmipsol(id,heursol) ! Load the heuristic solution
writeln_("Loaded solution Id: ",id)
setcallback(XPRS_CB_SOLNOTIFY,"solnotify")
end-if
delcell(heursol) ! Delete saved solution values
reset(SeqProblem) ! Delete subproblem definition
end-do
writeln_("(", gettime-starttime, "s) Best lower bound: ", cutoff)
! makespan >= cutoff
if ALG=2 then
MD:=max(m in RESOURCES) MAXDUR(m)
forall(m in RESOURCES) bbindex:=if(MAXDUR(m)=MD, m, bbindex)
writeln_("Bottelneck machine: ", bbindex)
! Add the subproblem that has provided the largest lower bound
sequencemachine(bbindex)
! Connect subproblem to main problem
forall(j in JOBS) 1 + sum(i in JOBS | i<j) (1-y(bbindex,i,j)) +
sum(i in JOBS | i>j) y(bbindex,j,i) = sum(k in JOBS) k*rank(j,k)
end-if
if ALG=1 then
! Re-inforce use of user solutions by local search MIP heuristics
setparam("XPRS_USERSOLHEURISTIC",3)
end-if
end-if ! ALG>0
setparam("XPRS_VERBOSE", true)
setparam("XPRS_MAXTIME", 5)
! Solve the problem: minimize latest completion time
minimize(makespan)
! Solution printing
writeln_("(", gettime-starttime, "s) Total completion time: ", getobjval)
forall(j in JOBS) write(strfmt(j,8))
writeln
forall(m in RESOURCES) do
write(strfmt((m+1),-3))
forall(j in JOBS)
if(DUR(j,RESIND(m,j))>0) then
write(strfmt(getsol(start(j,RESIND(m,j))),4), "-",
strfmt(getsol(start(j,RESIND(m,j)))+DUR(j,RESIND(m,j)),3))
else
write(strfmt(" ",6))
end-if
writeln
end-do
end-model
|
(!******************************************************
Mosel Example Problems
======================
file jobshopasc.mos
```````````````````
Job shop production planning,
second, generic formulation.`
-- Parallel version using cloning --
*** ATTENTION: This model will return an error if no ***
*** sufficient number of Xpress licences is available ***
(c) 2020 Fair Isaac Corporation
author: S. Heipcke, Apr. 2020
*******************************************************!)
model "B-3 Job shop (2) Clone"
uses "mmxprs", "mmjobs", "mmsystem"
parameters
DATAFILE = "mt10.dat" ! mt06.dat : Fisher and Thompson 6x6 instance
ALG = 1 ! 0: Default solving, 1: Add partial solution,
! 2: Augment Jobshop problem with one sequencing problem
MACH = 1 ! Subproblem identifier
MAXTHRD = 2 ! Max number of parallel threads for one inst.
end-parameters
declarations
! Shared data
NBJOBS: shared integer ! Number of jobs
NBRES: shared integer ! Number of resources
JOBS: shared range ! Set of jobs
TASKS: shared range ! Set of tasks (one per machine)
TASKSM1: shared range ! Set of tasks without last
RESOURCES: shared range ! Set of resources
DUR: shared array(JOBS,TASKS) of integer ! Durations of tasks
RESIND: shared array(RESOURCES,JOBS) of integer ! Task index per resource
MAXDUR: shared array(RESOURCES) of integer
BIGM: integer ! Used in formulation of master
cutoff,starttime: real ! Temp. value used in master
bbindex: integer ! Temp. value used in master
! Declarations for master model
start: array(JOBS,TASKS) of mpvar ! Start times of tasks
comp: array(JOBS,TASKS) of mpvar ! Completion times of tasks
makespan: mpvar ! Schedule completion time
y: dynamic array(RESOURCES,JOBS,JOBS) of mpvar ! Disjunction variables
! Declarations for sequencing subproblems
heursol: dynamic array(set of mpvar) of real
rank: array(JOBS,JOBS) of mpvar ! =1 if job j at position k
jcomp,tstart: array(JOBS) of mpvar ! Start time of job at position k
! Model and solution handling
SeqMod: array(RESOURCES) of Model ! Models
NOSOL=2 ! "No sol found" event
NEWSOL=3 ! "Solution found" event
pos: shared array(RESOURCES,JOBS) of integer ! Subproblem solutions
Makespan: shared array(RESOURCES) of real ! Subproblem makespan
end-declarations
!************ Data input (master problem) ************
procedure readdata
initializations from DATAFILE
NBJOBS NBRES
end-initializations
JOBS := 1..NBJOBS; finalize(JOBS)
TASKS := 1..NBRES ; finalize(TASKS)
TASKSM1 := 1..NBRES-1 ; finalize(TASKSM1)
RESOURCES := 0..NBRES-1 ; finalize(RESOURCES)
declarations
taskUse: array(JOBS,TASKS) of integer ! Resource use of tasks
end-declarations
initializations from DATAFILE
taskUse DUR as "taskDuration"
end-initializations
forall(m in RESOURCES,j in JOBS,t in TASKS | taskUse(j,t) = m) RESIND(m,j):=t
BIGM:=sum(j in JOBS,t in TASKS) DUR(j,t) ! Some (sufficiently) large value
forall(m in RESOURCES) MAXDUR(m):=sum(j in JOBS) DUR(j,RESIND(m,j))
end-procedure
!************ Create disjunctive constraints (master problem) ************
procedure disjunctiveconstraints(m:integer)
forall(i,j in JOBS | i<j) do
create(y(m,i,j))
y(m,i,j) is_binary !=1 if i>>j, =0 if i<<j
start(i,RESIND(m,i))+DUR(i,RESIND(m,i)) <=
start(j,RESIND(m,j))+BIGM*y(m,i,j)
start(j,RESIND(m,j))+DUR(j,RESIND(m,j)) <=
start(i,RESIND(m,i))+BIGM*(1-y(m,i,j))
end-do
end-procedure
! Alternative formulation of disjunctions
procedure disjunctiveconstraintsind(m:integer)
forall(i,j in JOBS | i<j) do
create(y(m,i,j))
y(m,i,j) is_binary !=1 if i>>j, =0 if i<<j
indicator(-1,y(m,i,j),
start(i,RESIND(m,i))+DUR(i,RESIND(m,i)) <= start(j,RESIND(m,j)))
indicator(1,y(m,i,j),
start(j,RESIND(m,j))+DUR(j,RESIND(m,j)) <= start(i,RESIND(m,i)) )
end-do
end-procedure
!************ Single machine sequencing subproblem ************
procedure sequencemachine(m:integer)
! One job per position
forall(k in JOBS) sum(j in JOBS) rank(j,k) = 1
! One position per job
forall(j in JOBS) sum(k in JOBS) rank(j,k) = 1
! Sequence of jobs
forall(k in 1..NBJOBS-1)
tstart(k+1) >=
tstart(k) + sum(j in JOBS) DUR(j,RESIND(m,j))*rank(j,k)
! Start times (release date = min total duration for preceding tasks)
forall(j in JOBS) REL(j):= sum(t in 1..RESIND(m,j)-1) DUR(j,t)
forall(j in JOBS) DURSUCC(j):= sum(t in RESIND(m,j)+1..NBRES) DUR(j,t)
forall(k in JOBS) tstart(k) >= sum(j in JOBS) REL(j)*rank(j,k)
! Completion times
forall(k in JOBS) jcomp(k) =
tstart(k) + sum(j in JOBS) (DUR(j,RESIND(m,j))+DURSUCC(j))*rank(j,k)
forall(j,k in JOBS) rank(j,k) is_binary
! Objective function: minimize latest completion time
forall(k in JOBS) makespan >= jcomp(k)
end-procedure
procedure solvesub(m:integer)
minimize(makespan) ! Solve the problem
! Solution reporting
if getprobstat=XPRS_OPT then
! writeln_("*** Machine ", m, ": ", getobjval)
forall(j in JOBS) pos(m,j):= round(sum(k in JOBS) k*rank(j,k).sol)
Makespan(m):=getobjval
! Send "solution found" signal
send(NEWSOL, getobjval)
else
send(NOSOL, 0)
end-if
end-procedure
!************ Status of loaded solutions (master) ************
public procedure solnotify(id:string, status:integer)
writeln_("Optimiser loaded solution ",id," status=",status)
end-procedure
!************ Main problem: Job-shop scheduling problem ************
procedure solvemaster
! Precedence constraints between last task of every job and makespan
forall(j in JOBS) makespan >= start(j,NBRES) + DUR(j,NBRES)
! Precedence constraints between the tasks of every job
forall(j in JOBS,t in TASKSM1)
start(j,t) + DUR(j,t) <= start(j,t+1)
! Disjunctions
forall(r in RESOURCES) disjunctiveconstraints(r)
! Linking start and completion times
forall(j in JOBS,t in TASKS) start(j,t)+DUR(j,t) = comp(j,t)
! Bound on latest completion time
makespan <= BIGM
starttime:=gettime
if ALG>0 then
! Solve the single machine sequencing problems
forall(m in RESOURCES) do
load(SeqMod(m)) ! Clone the current model
SeqMod(m).uid:= m
setworkdir(SeqMod(m), ".")
run(SeqMod(m), "MACH="+m +",MAXTHRD="+1)
end-do
tct:=0
while (tct<NBRES) do
wait ! Wait for the next event
Msg:= getnextevent ! Get the event
mid:= Msg.fromuid ! Get model number of sender
if getclass(Msg)=NEWSOL then ! Get the event class
if Makespan(mid)>cutoff then
cutoff:= Makespan(mid);
bbindex:=mid
end-if
writeln_("*** (", gettime-starttime, "s) Machine ", mid, ": ", Makespan(mid))
forall(i,j in JOBS | i<j ) heursol(y(mid,i,j)):= if(pos(mid,i)<pos(mid,j), 0, 1)
loadprob(makespan) ! Make sure problem is loaded
if ALG=1 then
id:="mach"+mid
addmipsol(id,heursol) ! Load the heuristic solution
writeln_("Loaded solution Id: ",id)
setcallback(XPRS_CB_SOLNOTIFY,"solnotify")
end-if
delcell(heursol) ! Delete saved solution values
elif getclass(Msg)=NOSOL then
writeln_("Subproblem ", mid, " has no solution. Stopping")
exit(1)
else
tct+=1
unload(SeqMod(mid)) ! Delete subproblem
end-if
end-do
writeln_("(", gettime-starttime, "s) Best lower bound: ", cutoff)
! makespan >= cutoff
if ALG=2 then
MD:=max(m in RESOURCES) MAXDUR(m)
forall(m in RESOURCES) bbindex:=if(MAXDUR(m)=MD, m, bbindex)
writeln_("Bottelneck machine: ", bbindex)
! Add the subproblem that has provided the largest lower bound
sequencemachine(bbindex)
! Connect subproblem to main problem
forall(j in JOBS) 1 + sum(i in JOBS | i<j) (1-y(bbindex,i,j)) +
sum(i in JOBS | i>j) y(bbindex,j,i) = sum(k in JOBS) k*rank(j,k)
end-if
if ALG=1 then
! Re-inforce use of user solutions by local search MIP heuristics
setparam("XPRS_USERSOLHEURISTIC",3)
end-if
end-if ! ALG>0
setparam("XPRS_VERBOSE", true)
setparam("XPRS_MAXTIME", 5)
! Solve the problem: minimize latest completion time
minimize(makespan)
end-procedure
!************ Solution printing (main problem) ************
procedure printsol
writeln_("(", gettime-starttime, "s) Total completion time: ", getobjval)
forall(j in JOBS) write(strfmt(j,8))
writeln
forall(m in RESOURCES) do
write(strfmt((m+1),-3))
forall(j in JOBS)
if(DUR(j,RESIND(m,j))>0) then
write(formattext("%4d-%3d", round(getsol(start(j,RESIND(m,j)))),
round(getsol(start(j,RESIND(m,j)))+DUR(j,RESIND(m,j)))))
else
write(strfmt(" ",6))
end-if
writeln
end-do
end-procedure
!****************************************************************
if getparam("sharingstatus")<=0 then
readdata
solvemaster
printsol
else
sequencemachine(MACH)
solvesub(MACH)
end-if
end-model
|
(!******************************************************
Mosel Example Problems
======================
file jobshopasp.mos
```````````````````
Job shop production planning,
second, generic formulation.`
-- Parallel version --
*** ATTENTION: This model will return an error if no ***
*** sufficient number of Xpress licences is available ***
(c) 2013 Fair Isaac Corporation
author: S. Heipcke, Jan. 2013, rev. Apr. 2020
*******************************************************!)
model "B-3 Job shop (2) Par"
uses "mmxprs", "mmjobs", "mmsystem"
parameters
DATAFILE = "mt10.dat" ! mt06.dat : Fisher and Thompson 6x6 instance
ALG = 1 ! 0: Default solving, 1: Add partial solution,
! 2: Augment Jobshop problem with one sequencing problem
end-parameters
declarations
NBJOBS: integer ! Number of jobs
NBRES: integer ! Number of resources
end-declarations
initializations from DATAFILE
NBJOBS NBRES
end-initializations
declarations
JOBS = 1..NBJOBS ! Set of jobs
TASKS = 1..NBRES ! Set of tasks (one per machine)
TASKSM1 = 1..NBRES-1 ! Set of tasks without last
RESOURCES = 0..NBRES-1 ! Set of resources
taskUse: array(JOBS,TASKS) of integer ! Resource use of tasks
DUR: array(JOBS,TASKS) of integer ! Durations of tasks
RESIND: array(RESOURCES,JOBS) of integer ! Task index per resource
BIGM: integer
MAXDUR: array(RESOURCES) of integer
cutoff: real
bbindex: integer
end-declarations
initializations from DATAFILE
taskUse DUR as "taskDuration"
end-initializations
forall(m in RESOURCES,j in JOBS,t in TASKS | taskUse(j,t) = m) RESIND(m,j):=t
BIGM:=sum(j in JOBS,t in TASKS) DUR(j,t) ! Some (sufficiently) large value
forall(m in RESOURCES) MAXDUR(m):=sum(j in JOBS) DUR(j,RESIND(m,j))
declarations
start: array(JOBS,TASKS) of mpvar ! Start times of tasks
comp: array(JOBS,TASKS) of mpvar ! Completion times of tasks
makespan: mpvar ! Schedule completion time
y: dynamic array(RESOURCES,JOBS,JOBS) of mpvar ! Disjunction variables
heursol: dynamic array(set of mpvar) of real
rank: array(JOBS,JOBS) of mpvar ! =1 if job j at position k
jcomp,tstart: array(JOBS) of mpvar ! Start time of job at position k
SeqMod: array(RESOURCES) of Model ! Models
NOSOL=2 ! "No sol found" event
NEWSOL=3 ! "Solution found" event
pos: array(JOBS) of integer ! Subproblem solution
Makespan: real ! Subproblem makespan
end-declarations
! **** Create disjunctive constraints ****
procedure disjunctiveconstraints(m:integer)
forall(i,j in JOBS | i<j) do
create(y(m,i,j))
y(m,i,j) is_binary !=1 if i>>j, =0 if i<<j
start(i,RESIND(m,i))+DUR(i,RESIND(m,i)) <=
start(j,RESIND(m,j))+BIGM*y(m,i,j)
start(j,RESIND(m,j))+DUR(j,RESIND(m,j)) <=
start(i,RESIND(m,i))+BIGM*(1-y(m,i,j))
end-do
end-procedure
! **** Single machine sequencing problem ****
procedure sequencemachine(m:integer)
! One job per position
forall(k in JOBS) sum(j in JOBS) rank(j,k) = 1
! One position per job
forall(j in JOBS) sum(k in JOBS) rank(j,k) = 1
! Sequence of jobs
forall(k in 1..NBJOBS-1)
tstart(k+1) >=
tstart(k) + sum(j in JOBS) DUR(j,RESIND(m,j))*rank(j,k)
! Start times (release date = min total duration for preceding tasks)
forall(j in JOBS) REL(j):= sum(t in 1..RESIND(m,j)-1) DUR(j,t)
forall(j in JOBS) DURSUCC(j):= sum(t in RESIND(m,j)+1..NBRES) DUR(j,t)
forall(k in JOBS) tstart(k) >= sum(j in JOBS) REL(j)*rank(j,k)
! Completion times
forall(k in JOBS) jcomp(k) =
tstart(k) + sum(j in JOBS) (DUR(j,RESIND(m,j))+DURSUCC(j))*rank(j,k)
forall(j,k in JOBS) rank(j,k) is_binary
! Objective function: minimize latest completion time
forall(k in JOBS) makespan >= jcomp(k)
end-procedure
! **** Status of loaded solutions ****
public procedure solnotify(id:string, status:integer)
writeln_("Optimiser loaded solution ",id," status=",status)
end-procedure
! **** Main problem: Job-shop scheduling problem ****
! Precedence constraints between last task of every job and makespan
forall(j in JOBS) makespan >= start(j,NBRES) + DUR(j,NBRES)
! Precedence constraints between the tasks of every job
forall(j in JOBS,t in TASKSM1)
start(j,t) + DUR(j,t) <= start(j,t+1)
! Disjunctions
forall(r in RESOURCES) disjunctiveconstraints(r)
! Linking start and completion times
forall(j in JOBS,t in TASKS) start(j,t)+DUR(j,t) = comp(j,t)
! Bound on latest completion time
makespan <= BIGM
starttime:=gettime
if ALG>0 then
! Compile submodel and prepare submodel data
if compile("jobseq.mos")<>0 then exit(1); end-if
initializations to "bin:shmem:jsdata"
DUR RESIND MAXDUR
end-initializations
! Solve the single machine sequencing problems
forall(m in RESOURCES) do
load(SeqMod(m), "jobseq.bim")
SeqMod(m).uid:= m
setworkdir(SeqMod(m), ".")
run(SeqMod(m), "MACH="+m +",NBJOBS="+NBJOBS +",NBRES="+NBRES +
",DATAFILE=bin:shmem:jsdata,MAXTHRD="+1)
end-do
tct:=0
while (tct<NBRES) do
wait ! Wait for the next event
Msg:= getnextevent ! Get the event
mid:= Msg.fromuid ! Get model number of sender
if getclass(Msg)=NEWSOL then ! Get the event class
initializations from "bin:shmem:sol"+mid
pos Makespan
end-initializations
if Makespan>cutoff then
cutoff:= Makespan;
bbindex:=mid
end-if
writeln_("*** (", gettime-starttime, "s) Machine ", mid, ": ", Makespan)
forall(i,j in JOBS | i<j ) heursol(y(mid,i,j)):= if(pos(i)<pos(j), 0, 1)
loadprob(makespan)
if ALG=1 then
id:="mach"+mid
addmipsol(id,heursol) ! Load the heuristic solution
writeln_("Loaded solution Id: ",id)
setcallback(XPRS_CB_SOLNOTIFY,"solnotify")
end-if
delcell(heursol) ! Delete saved solution values
fdelete("bin:shmem:sol"+mid)
elif getclass(Msg)=NOSOL then
writeln_("Subproblem ", mid, " has no solution. Stopping")
exit(1)
else
tct+=1
unload(SeqMod(mid)) ! Delete subproblem
end-if
end-do
writeln_("(", gettime-starttime, "s) Best lower bound: ", cutoff)
! makespan >= cutoff
if ALG=2 then
MD:=max(m in RESOURCES) MAXDUR(m)
forall(m in RESOURCES) bbindex:=if(MAXDUR(m)=MD, m, bbindex)
writeln_("Bottelneck machine: ", bbindex)
! Add the subproblem that has provided the largest lower bound
sequencemachine(bbindex)
! Connect subproblem to main problem
forall(j in JOBS) 1 + sum(i in JOBS | i<j) (1-y(bbindex,i,j)) +
sum(i in JOBS | i>j) y(bbindex,j,i) = sum(k in JOBS) k*rank(j,k)
end-if
if ALG=1 then
! Re-inforce use of user solutions by local search MIP heuristics
setparam("XPRS_USERSOLHEURISTIC",3)
end-if
end-if ! ALG>0
setparam("XPRS_VERBOSE", true)
setparam("XPRS_MAXTIME", 5)
! Solve the problem: minimize latest completion time
minimize(makespan)
! Solution printing
writeln_("(", gettime-starttime, "s) Total completion time: ", getobjval)
forall(j in JOBS) write(strfmt(j,8))
writeln
forall(m in RESOURCES) do
write(strfmt((m+1),-3))
forall(j in JOBS)
if(DUR(j,RESIND(m,j))>0) then
write(strfmt(getsol(start(j,RESIND(m,j))),4), "-",
strfmt(getsol(start(j,RESIND(m,j)))+DUR(j,RESIND(m,j)),3))
else
write(strfmt(" ",6))
end-if
writeln
end-do
end-model
|
(!******************************************************
Mosel Example Problems
======================
file jobseq.mos
```````````````
Job shop production planning.
Single machine sequencing subproblem for jobshopasd.mos
*** Not intended to be run standalone - run from jobshopasp.mos ***
(c) 2013 Fair Isaac Corporation
author: S. Heipcke, Jan. 2013
*******************************************************!)
model "Sequencing"
uses "mmxprs", "mmjobs"
parameters
MACH = 1 ! Subproblem identifier
NBJOBS = 10 ! Number of jobs
NBRES = 10 ! Number of resources
DATAFILE = "mt10.dat"
MAXTHRD = 2 ! Max number of parallel threads for one inst.
end-parameters
declarations
JOBS = 1..NBJOBS ! Set of jobs
TASKS = 1..NBRES ! Set of tasks (one per machine)
RESOURCES = 0..NBRES-1 ! Set of resources
DUR: array(JOBS,TASKS) of integer ! Durations of tasks
RESIND: array(RESOURCES,JOBS) of integer ! Task index per resource
MAXDUR: array(RESOURCES) of integer
end-declarations
initializations from DATAFILE
DUR RESIND MAXDUR
end-initializations
declarations
makespan: mpvar ! Schedule completion time
rank: array(JOBS,JOBS) of mpvar ! =1 if job j at position k
jcomp,tstart: array(JOBS) of mpvar ! Start time of job at position k
NOSOL=2 ! "No sol found" event
NEWSOL=3 ! "Solution found" event
end-declarations
! One job per position
forall(k in JOBS) sum(j in JOBS) rank(j,k) = 1
! One position per job
forall(j in JOBS) sum(k in JOBS) rank(j,k) = 1
! Sequence of jobs
forall(k in 1..NBJOBS-1)
tstart(k+1) >=
tstart(k) + sum(j in JOBS) DUR(j,RESIND(MACH,j))*rank(j,k)
! Start times (release date = min total duration for preceding tasks)
forall(j in JOBS) REL(j):= sum(t in 1..RESIND(MACH,j)-1) DUR(j,t)
forall(j in JOBS) DURSUCC(j):= sum(t in RESIND(MACH,j)+1..NBRES) DUR(j,t)
forall(k in JOBS) tstart(k) >= sum(j in JOBS) REL(j)*rank(j,k)
! Completion times
forall(k in JOBS) jcomp(k) =
tstart(k) + sum(j in JOBS) (DUR(j,RESIND(MACH,j))+DURSUCC(j))*rank(j,k)
forall(j,k in JOBS) rank(j,k) is_binary
! Objective function: minimize latest completion time
forall(k in JOBS) makespan >= jcomp(k)
! Solving
setparam("XPRS_THREADS", MAXTHRD) ! Limit the number of threads
minimize(makespan) ! Solve the problem
! Solution reporting
if getprobstat=XPRS_OPT then
! writeln_("*** Machine ", MACH, ": ", getobjval)
forall(j in JOBS) pos(j):= round(sum(k in JOBS) k*rank(j,k).sol)
initializations to "bin:shmem:sol"+MACH
pos
evaluation of getobjval as "Makespan"
end-initializations
! Send "solution found" signal
send(NEWSOL, getobjval)
else
send(NOSOL, 0)
end-if
end-model
|