Initializing help system before first use

Results for question 1

The model in the previous section prints the following output. The earliest completion time is 64 weeks. For every operation (task), its start time or interval of possible start times is indicated.

Earliest possible completion time: 64
1: 0
2: 2
3: 18
4: [18..29]
5: 27
6: 37
7: [26..61]
8: [43..59]
9: 43
10: [26..59]
11: [43..58]
12: 52
13: [28..63]
14: [18..53]
15: [26..60]
16: [46..61]
17: 54
18: 63
19: 64