producer_consumer
function producer_consumer(starts:array(range) of cpvar, ends:array(range) of cpvar, durations:array(range) of cpvar, productions:array(range) of cpvar, prod_sizes:array(range) of cpvar, consumptions:array(range) of cpvar, conso_sizes:array(range) of cpvar, C:array(range) of integer) : cpctr
 | 
     starts 
     | 
     array of starting times
     | 
| 
     ends 
     | 
     array of ending times
     | 
| 
     durations 
     | 
     array of durations
     | 
| 
     productions 
     | 
     array of tasks' requirements
     | 
| 
     prod_sizes 
     | 
     array of tasks' productions
     | 
| 
     consumptions 
     | 
     array of tasks' provisions
     | 
| 
     conso_sizes 
     | 
     array of tasks' consumptions
     | 
| 
     C 
     | 
     initial resource capacity array indexed by time
     | 
model "Cumulative Scheduling"
 uses "kalis"
 setparam("KALIS_DEFAULT_LB",0)
 setparam("KALIS_DEFAULT_UB",100)
 declarations
 ! Task indices
  Masonry = 1; Carpentry= 2; Roofing       = 3; Windows      = 4
  Facade  = 5; Garden   = 6; Plumbing      = 7; Ceiling      = 8
  Painting= 9; MovingIn =10; InitialPayment=11; SecondPayment=12
  BUILDTASKS = 1..10
  PAYMENTS = 11..12
  TASKS = BUILDTASKS+PAYMENTS
  TNAMES: array(TASKS) of string
  obj:cpvar                                ! Objective variable
  starts   : array(TASKS) of cpvar         ! Start times variables
  ends     : array(TASKS) of cpvar         ! Completion times
  durations: array(TASKS) of cpvar         ! Durations of tasks
  consos   : dynamic array(TASKS) of cpvar ! Res. consumptions
  sizes    : dynamic array(TASKS) of cpvar ! Consumption sizes
  prods    : dynamic array(TASKS) of cpvar ! Res. production
  sizep    : dynamic array(TASKS) of cpvar ! Production sizes
  Strategy : cpbranching                   ! Branching strategy
 end-declarations
 TNAMES:: (1..12)["Masonry", "Carpentry", "Roofing", "Windows",
           "Facade", "Garden", "Plumbing", "Ceiling", "Painting",
	   "MovingIn", "InitialPayment", "SecondPayment"]
! Setting the names of the variables
  forall(j in TASKS) do
    starts(j).name := TNAMES(j)+".start"
    ends(j).name := TNAMES(j)+".end"
    durations(j).name := TNAMES(j)+".duration"
  end-do
! Creating consumption variables
  forall(j in BUILDTASKS) do
    create(sizes(j))
    sizes(j).name := TNAMES(j)+".size"
    create(consos(j))
    consos(j).name := TNAMES(j)+".conso"
  end-do
! Setting durations of building tasks
 durations(Masonry) =7; durations(Carpentry)=3; durations(Roofing) =1
 durations(Windows) =1; durations(Facade)   =2; durations(Garden)  =1
 durations(Plumbing)=8; durations(Ceiling)  =3; durations(Painting)=2
 durations(MovingIn)=1
! Precedence constraints among building tasks
 starts(Carpentry) >= ends(Masonry)
 starts(Roofing)   >= ends(Carpentry)
 starts(Windows)   >= ends(Roofing)
 starts(Facade)    >= ends(Roofing)
 starts(Garden)    >= ends(Roofing)
 starts(Plumbing)  >= ends(Masonry)
 starts(Ceiling)   >= ends(Masonry)
 starts(Painting)  >= ends(Ceiling)
 starts(MovingIn)  >= ends(Windows)
 starts(MovingIn)  >= ends(Facade)
 starts(MovingIn)  >= ends(Garden)
 starts(MovingIn)  >= ends(Painting)
! Setting task consumptions
 consos(Masonry)  = 7; consos(Carpentry) = 3; consos(Roofing)  = 1
 consos(Windows)  = 1; consos(Facade)    = 2; consos(Garden)   = 1
 consos(Plumbing) = 8; consos(Ceiling)   = 3; consos(Painting) = 2
 consos(MovingIn) = 1
! Production (amount) of payment tasks
 forall(j in PAYMENTS) do
  create(prods(j))
  prods(j).name := TNAMES(j)+".prod"
  create(sizep(j))
  sizep(j).name := TNAMES(j)+".sizep"
 end-do
! Payment data
 prods(InitialPayment)    = 20; prods(SecondPayment)     = 9
 durations(InitialPayment) = 1; durations(SecondPayment) = 1
 starts(InitialPayment)    = 0; starts(SecondPayment)    = 15
! Objective: makespan of the schedule
 obj = maximum({ ends(Masonry) , ends(Carpentry), ends(Roofing),
         ends(Windows), ends(Facade), ends(Garden), ends(Plumbing),
	 ends(Ceiling), ends(Painting), ends(MovingIn)})
! Posting the producer_consumer constraint
 producer_consumer(starts,ends,durations,prods,sizep,consos,sizes)
! Setting the search strategy
 Strategy:= assign_var(KALIS_SMALLEST_MIN, KALIS_MIN_TO_MAX, starts)
 cp_set_branching(Strategy)
! Find the optimal solution
 if cp_minimize(obj) then
  writeln("Minimum makespan: ", obj.sol)
  forall(j in BUILDTASKS)
    writeln(TNAMES(j), ": ", starts(j).sol, " - ", ends(j).sol)
 else
  writeln("No solution found")
 end-if
end-model
 © 2001-2021 Fair Isaac Corporation. All rights reserved. This documentation is the property of Fair Isaac Corporation (“FICO”). Receipt or possession of this documentation does not convey rights to disclose, reproduce, make derivative works, use, or allow others to use it except solely for internal evaluation purposes to determine whether to purchase a license to the software described in this documentation, or as otherwise set forth in a written software license agreement between you and FICO (or a FICO affiliate). Use of this documentation and the software described in it must conform strictly to the foregoing permitted uses, and no other use is permitted.
 