getend

Purpose
Retrieves the 'end' variable of a task.
A cptask is represented by three cpvar:
  • 'start' representing the start time of the task
  • 'end' representing the completion time of the task
  • 'duration' representing the duration of the task.
These three structural variables are linked with the following constraint: start + duration ≤ end.
The 'end' variable represents two specific parameters of the task: the Earliest Completion Time (ECT, represented by its lower bound) and its Latest Completion Time (LCT, represented by its upper bound). The graphic below illustrates these properties:
Scheduling/task.png
Synopsis
function getend(t:cptask) : cpvar
Argument
the task
Return value
The cpvar representing the completion time of t
Related topics

© 2001-2024 Fair Isaac Corporation. All rights reserved. This documentation is the property of Fair Isaac Corporation (“FICO”). Receipt or possession of this documentation does not convey rights to disclose, reproduce, make derivative works, use, or allow others to use it except solely for internal evaluation purposes to determine whether to purchase a license to the software described in this documentation, or as otherwise set forth in a written software license agreement between you and FICO (or a FICO affiliate). Use of this documentation and the software described in it must conform strictly to the foregoing permitted uses, and no other use is permitted.