'producer_consumer' constraints: solving a resource-constrained project scheduling problem


Type: Resource-constrained project planning
Rating: 2 (easy-medium)
Description: So-called 'producer_consumer' relations combine tasks that produce or consume quantities of the same non-renewable resource. Such problems may be modeled in two ways, namely
  • using 'producer_consumer' constraints (producer_consumer_alt.mos), or
  • using 'task' and 'resource' model objects that are configured correspondingly (producer_consumer.mos)
File(s): producer_consumer.mos, producer_consumer_alt.mos, producer_consumer_alt_graph.mos


producer_consumer.mos
(!****************************************************************
   CP example problems
   ===================
   
   file producer_consumer.mos
   ``````````````````````````
   Resource-constrained project planning problem (construction of 
   a house) modeled with task and resource objects.

   *** This model cannot be run with a Community Licence ***  

   (c) 2008 Artelys S.A. and Fair Isaac Corporation

*****************************************************************!)
model "Producer Consumer"  
 uses "kalis"
 
 declarations
  Masonry, Carpentry, Roofing, Windows, Facade, Garden, Plumbing, 
    Ceiling, Painting, MovingIn : cptask    ! Declaration of tasks
  money_available : cpresource              ! Resource declaration   
 end-declarations

! 'money_available' is a cumulative resource with max. amount of 29$ 
 set_resource_attributes(money_available,KALIS_DISCRETE_RESOURCE,29)

! Limit resource availability to 20$ in the time interval [0,14]
 setcapacity(money_available, 0, 14, 20)

! Setting the task durations and predecessor sets
 set_task_attributes(Masonry  , 7 ) 
 set_task_attributes(Carpentry, 3, {Masonry} )
 set_task_attributes(Roofing  , 1, {Carpentry} )
 set_task_attributes(Windows  , 1, {Roofing} )
 set_task_attributes(Facade   , 2, {Roofing} )
 set_task_attributes(Garden   , 1, {Roofing} )
 set_task_attributes(Plumbing , 8, {Masonry} )
 set_task_attributes(Ceiling  , 3, {Masonry} )
 set_task_attributes(Painting , 2, {Ceiling} )
 set_task_attributes(MovingIn , 1, {Windows,Facade,Garden,Painting})

! Setting the resource consumptions
 consumes(Masonry  , 7, money_available )
 consumes(Carpentry, 3, money_available )
 consumes(Roofing  , 1, money_available )
 consumes(Windows  , 1, money_available )
 consumes(Facade   , 2, money_available )
 consumes(Garden   , 1, money_available )
 consumes(Plumbing , 8, money_available )
 consumes(Ceiling  , 3, money_available )
 consumes(Painting , 2, money_available )
 consumes(MovingIn , 1, money_available )

! Find the optimal schedule (minimizing the makespan)
 if cp_minimize(getmakespan) then	
   cp_show_sol		
 else
   writeln("No solution found")
 end-if

end-model

producer_consumer_alt.mos
(!****************************************************************
   CP example problems
   ===================
   
   file producer_consumer_alt.mos
   ``````````````````````````````
   Resource-constrained project planning problem (construction of 
   a house) modeled with a producer-consumer constraint.

   *** This model cannot be run with a Community Licence *** 

   (c) 2008 Artelys S.A. and Fair Isaac Corporation
       Creation: 2007, rev. Mar. 2013
*****************************************************************!)
model "Cumulative Scheduling"  
 uses "kalis" 

 setparam("KALIS_DEFAULT_LB",0)
 setparam("KALIS_DEFAULT_UB",100)

 declarations
 ! Task indices
  Masonry = 1; Carpentry= 2; Roofing       = 3; Windows      = 4
  Facade  = 5; Garden   = 6; Plumbing      = 7; Ceiling      = 8
  Painting= 9; MovingIn =10; InitialPayment=11; SecondPayment=12
  BUILDTASKS = 1..10
  PAYMENTS = 11..12
  TASKS = BUILDTASKS+PAYMENTS
  TNAMES: array(TASKS) of string
  
  obj:cpvar                                ! Objective variable
  starts   : array(TASKS) of cpvar         ! Start times variables  
  ends     : array(TASKS) of cpvar         ! Completion times  
  durations: array(TASKS) of cpvar         ! Durations of tasks  
  consos   : dynamic array(TASKS) of cpvar ! Res. consumptions   
  sizes    : dynamic array(TASKS) of cpvar ! Consumption sizes 
  prods    : dynamic array(TASKS) of cpvar ! Res. production  
  sizep    : dynamic array(TASKS) of cpvar ! Production sizes 
  Strategy : cpbranching                   ! Branching strategy  
 end-declarations

 TNAMES:: (1..12)["Masonry", "Carpentry", "Roofing", "Windows",  
           "Facade", "Garden", "Plumbing", "Ceiling", "Painting", 
	   "MovingIn", "InitialPayment", "SecondPayment"]
 
! Setting the names of the variables 
  forall(j in TASKS) do
    starts(j).name := TNAMES(j)+".start"
    ends(j).name := TNAMES(j)+".end"
    durations(j).name := TNAMES(j)+".duration"
  end-do

! Creating consumption variables
  forall(j in BUILDTASKS) do
    create(sizes(j))
    sizes(j).name := TNAMES(j)+".size"
    create(consos(j))
    consos(j).name := TNAMES(j)+".conso"
  end-do

! Setting durations of building tasks
 durations(Masonry) =7; durations(Carpentry)=3; durations(Roofing) =1
 durations(Windows) =1; durations(Facade)   =2; durations(Garden)  =1
 durations(Plumbing)=8; durations(Ceiling)  =3; durations(Painting)=2
 durations(MovingIn)=1

! Precedence constraints among building tasks
 starts(Carpentry) >= ends(Masonry)
 starts(Roofing)   >= ends(Carpentry)
 starts(Windows)   >= ends(Roofing)
 starts(Facade)    >= ends(Roofing)
 starts(Garden)    >= ends(Roofing)
 starts(Plumbing)  >= ends(Masonry)
 starts(Ceiling)   >= ends(Masonry)
 starts(Painting)  >= ends(Ceiling)
 starts(MovingIn)  >= ends(Windows)
 starts(MovingIn)  >= ends(Facade)
 starts(MovingIn)  >= ends(Garden)
 starts(MovingIn)  >= ends(Painting)

! Setting task consumptions
 consos(Masonry)  = 7; consos(Carpentry) = 3; consos(Roofing)  = 1 
 consos(Windows)  = 1; consos(Facade)    = 2; consos(Garden)   = 1 
 consos(Plumbing) = 8; consos(Ceiling)   = 3; consos(Painting) = 2 
 consos(MovingIn) = 1

! Production (amount) of payment tasks
 forall(j in PAYMENTS) do
  create(prods(j))
  prods(j).name := TNAMES(j)+".prod"
  create(sizep(j))
  sizep(j).name := TNAMES(j)+".sizep"
 end-do

! Payment data
 prods(InitialPayment)    = 20; prods(SecondPayment)     = 9
 durations(InitialPayment) = 1; durations(SecondPayment) = 1
 starts(InitialPayment)    = 0; starts(SecondPayment)    = 15


! Objective: makespan of the schedule
 obj = maximum({ ends(Masonry) , ends(Carpentry), ends(Roofing), 
         ends(Windows), ends(Facade), ends(Garden), ends(Plumbing),
	 ends(Ceiling), ends(Painting), ends(MovingIn)})

! Posting the producer_consumer constraint
 producer_consumer(starts,ends,durations,prods,sizep,consos,sizes)

! Setting the search strategy
 Strategy:= assign_var(KALIS_SMALLEST_MIN, KALIS_MIN_TO_MAX, starts)
 cp_set_branching(Strategy) 
 
! Find the optimal solution
 if cp_minimize(obj) then 
  writeln("Minimum makespan: ", obj.sol)
  forall(j in BUILDTASKS)
    writeln(TNAMES(j), ": ", starts(j).sol, " - ", ends(j).sol) 
 else
  writeln("No solution found")
 end-if

end-model


producer_consumer_alt_graph.mos
(!****************************************************************
   CP example problems
   ===================
   
   file producer_consumer_graph.mos
   ````````````````````````````````
   Resource-constrained project planning problem (construction of 
   a house) modeled with a producer-consumer constraint.

   *** This model cannot be run with a Community Licence ***  

   (c) 2008 Artelys S.A. and Fair Isaac Corporation
       Creation: 2007, rev. Sep. 2017
*****************************************************************!)
model "Cumulative Scheduling"  
 uses "kalis","mmsvg" 

 forward procedure draw_solution 

 setparam("KALIS_DEFAULT_LB",0)
 setparam("KALIS_DEFAULT_UB",100)

 declarations
  ! Task indices
  Masonry  = 1; Carpentry = 2; Roofing        = 3; Windows        = 4
  Facade   = 5; Garden    = 6; Plumbing       = 7; Ceiling        = 8
  Painting = 9; MovingIn = 10; InitialPayment = 11; SecondPayment = 12
  BUILDTASKS = 1..10
  PAYMENTS = 11..12
  TASKS = BUILDTASKS+PAYMENTS
  TNAMES: array(TASKS) of string
  
  obj:cpvar                                ! Objective variable
  starts   : array(TASKS) of cpvar         ! Start times of the tasks  
  ends     : array(TASKS) of cpvar         ! Completion times of the tasks  
  durations: array(TASKS) of cpvar         ! Durations of the tasks  
  consos   : dynamic array(TASKS) of cpvar ! Res. consumptions of the tasks   
  sizes    : dynamic array(TASKS) of cpvar ! Consumption sizes (= conso x dur)  
  prods    : dynamic array(TASKS) of cpvar ! Res. production of the tasks  
  sizep    : dynamic array(TASKS) of cpvar ! Production sizes (= prod x dur)
  Strategy : array(range) of cpbranching   ! Branching strategy  
 end-declarations

 TNAMES:: (1..12)["Masonry", "Carpentry", "Roofing", "Windows", "Facade", 
           "Garden", "Plumbing", "Ceiling", "Painting", "MovingIn",
	   "InitialPayment", "SecondPayment"]
 
! Setting the names of the variables 
  forall(j in TASKS) do
    starts(j).name := TNAMES(j)+".start"
    ends(j).name := TNAMES(j)+".end"
    durations(j).name := TNAMES(j)+".duration"
  end-do

! Creating consumption variables
  forall(j in BUILDTASKS) do
    create(sizes(j))
    sizes(j).name := TNAMES(j)+".size"
    create(consos(j))
    consos(j).name := TNAMES(j)+".conso"
  end-do

! Setting durations of building tasks
 durations(Masonry)  = 7; durations(Carpentry) = 3; durations(Roofing)  = 1
 durations(Windows)  = 1; durations(Facade)    = 2; durations(Garden)   = 1
 durations(Plumbing) = 8; durations(Ceiling)   = 3; durations(Painting) = 2
 durations(MovingIn) = 1

! Precedence constraints among building tasks
 starts(Carpentry) >= ends(Masonry)
 starts(Roofing)   >= ends(Carpentry)
 starts(Windows)   >= ends(Roofing)
 starts(Facade)    >= ends(Roofing)
 starts(Garden)    >= ends(Roofing)
 starts(Plumbing)  >= ends(Masonry)
 starts(Ceiling)   >= ends(Masonry)
 starts(Painting)  >= ends(Ceiling)
 starts(MovingIn)  >= ends(Windows)
 starts(MovingIn)  >= ends(Facade)
 starts(MovingIn)  >= ends(Garden)
 starts(MovingIn)  >= ends(Painting)

! Setting task consumptions
 consos(Masonry)  = 7; consos(Carpentry) = 3; consos(Roofing)  = 1 
 consos(Windows)  = 1; consos(Facade)    = 2; consos(Garden)   = 1 
 consos(Plumbing) = 8; consos(Ceiling)   = 3; consos(Painting) = 2 
 consos(MovingIn) = 1

! Production (amount) of payment tasks
 forall(j in PAYMENTS) do
  create(prods(j))
  prods(j).name := TNAMES(j)+".prod"
  create(sizep(j))
  sizep(j).name := TNAMES(j)+".sizep"
 end-do

! Payment data
 prods(InitialPayment)    = 20; prods(SecondPayment)     = 9
 durations(InitialPayment) = 1; durations(SecondPayment) = 1
 starts(InitialPayment)    = 0; starts(SecondPayment)    = 15

! Objective: makespan of the schedule
 obj = maximum({ ends(Masonry) , ends(Carpentry), ends(Roofing), ends(Windows), ends(Facade), ends(Garden), ends(Plumbing), ends(Ceiling), ends(Painting), ends(MovingIn)})

! Posting the producer_consumer constraint
 producer_consumer(starts, ends, durations, prods, sizep, consos, sizes)

! Setting the search strategy
 Strategy(0) := assign_var(KALIS_SMALLEST_MIN, KALIS_MIN_TO_MAX, starts)
 cp_set_branching(Strategy) 
 
! Find the optimal solution
 if cp_minimize(obj) then 
  cp_show_sol
  draw_solution 
 else
  writeln("No solution found")
 end-if

! Pretty display of the solution as an SVG user graph 
 procedure draw_solution     
  ind := 1
  mkspan := 0
  
  RES := 1
  HORIZON := getub(obj)
  forall(t in 0..HORIZON) histogram(RES,t) := 0
  svgaddgroup("TextPlot", "", SVG_BLACK)               

  setrandseed(17)
  forall(t in BUILDTASKS) do       
    svgaddgroup("G"+TNAMES(t), TNAMES(t), svgcolor(20+round(random*200),
                20+round(random*200), 20+round(random*200)))
    svgsetstyle(SVG_FILL,SVG_CURRENT)
    svgsetstyle(SVG_OPACITY,0.65)
    startt := getsol(starts(t))
    endt   := getsol(ends(t))
    uset   := getsol(consos(t))
    if mkspan < endt then
      mkspan := endt
    end-if
    svgaddrectangle(startt, ind, endt-startt, uset)
  !  svgaddtext(startt+1, ind-4, "t"+t)
    forall(h in startt..HORIZON) histogram(RES,h) -= uset
    ind += uset          
  end-do
   
  forall(t in PAYMENTS) do              
    svgaddgroup("P"+TNAMES(t), TNAMES(t), SVG_BLUE)
    svgsetstyle(SVG_FILL,SVG_CURRENT)
    svgsetstyle(SVG_FILLOPACITY,0.5)
    startt := getsol(starts(t))
    endt   := getsol(ends(t))
    uset   := getsol(prods(t))
    if mkspan < endt then
      mkspan := endt
    end-if
    svgaddrectangle(startt, (RES*-20), endt-startt, uset)
    svgaddtext(startt,RES*-21,"Payment "+t)
    forall (h in startt..HORIZON) histogram(RES,h) += uset
  end-do
  svgaddtext("TextPlot", mkspan, 0, "MakeSpan = " + mkspan)
  svgaddgroup("Money", "Money available ", SVG_RED)            
  svgsetstyle(SVG_FILL,SVG_CURRENT)
  svgsetstyle(SVG_FILLOPACITY,0.65)
  svgaddpolygon(sum(h in 0..mkspan-1)[h, ((RES*-20)+histogram(RES,h)), h+1, ((RES*-20)+histogram(RES,h))]+[mkspan,RES*-20,0,RES*-20])
 
  svgsetgraphscale(10)
  svgsetgraphviewbox(0,-25*RES, mkspan+10, 25*RES+ind)
  svgsetgraphlabels("Time","")

  svgsave("prodcons.svg")
  svgrefresh
  svgwaitclose("Close browser window to terminate model execution.", 1)
 end-procedure
end-model


© 2001-2025 Fair Isaac Corporation. All rights reserved. This documentation is the property of Fair Isaac Corporation (“FICO”). Receipt or possession of this documentation does not convey rights to disclose, reproduce, make derivative works, use, or allow others to use it except solely for internal evaluation purposes to determine whether to purchase a license to the software described in this documentation, or as otherwise set forth in a written software license agreement between you and FICO (or a FICO affiliate). Use of this documentation and the software described in it must conform strictly to the foregoing permitted uses, and no other use is permitted.