Sequencing jobs on a single machine


Type: Sequencing jobs on a machine
Rating: 3 (intermediate)
Description: A set of tasks (or jobs) is to be processed on a single machine. The execution of tasks is non-preemptive (that is, an operation may not be interrupted before its completion). For every task its release date, due date, and duration are given. The model shows how to minimize the total processing time, the average processing time, and the total tardiness (that is, the amount of time by which the completion of jobs exceeds their respective due dates).
File(s): sequencing_graph.mos
Data file(s): sequencing.dat


sequencing_graph.mos
(!******************************************************
   Mosel Example Problems
   ======================

   file sequencing.mos
   ```````````````````
   TYPE:         Sequencing jobs on a machine (single machine scheduling)
   DIFFICULTY:   3
   FEATURES:     MIP problem with 3 different objectives; `procedure' 
                 for solution printing, `if-then'
   DESCRIPTION:  A set of tasks (or jobs) is to be processed on a single 
                 machine. The execution of tasks is non-preemptive (that is, 
                 an operation may not be interrupted before its completion). 
                 For every task its release date, due date, and duration are 
                 given. 
                 The model shows how to minimize the total processing time, 
                 the average processing time, and the total tardiness (that 
                 is, the amount of time by which the completion of jobs 
                 exceeds their respective due dates).     
   FURTHER INFO: `Applications of optimization with Xpress-MP', 
                 Section 7.4 `Sequencing jobs on a bottleneck machine'
   
   (c) 2008 Fair Isaac Corporation
       author: S. Heipcke, 2002, rev. Sep. 2017
*******************************************************!)

model "Sequencing"
 uses "mmxprs", "mmsvg", "mmsystem"

 forward procedure print_sol(obj:integer)
 forward procedure draw_sol(obj:integer)
 
 declarations   
  NJ = 7                          ! Number of jobs
  JOBS=1..NJ

  REL: array(JOBS) of integer     ! Release dates of jobs
  DUR: array(JOBS) of integer     ! Durations of jobs
  DUE: array(JOBS) of integer     ! Due dates of jobs

  rank: array(JOBS,JOBS) of mpvar ! =1 if job j at position k
  start: array(JOBS) of mpvar     ! Start time of job at position k
  comp: array(JOBS) of mpvar      ! Completion time of job at position k
  late: array(JOBS) of mpvar      ! Lateness of job at position k
  finish: mpvar                   ! Completion time of the entire schedule
 end-declarations
 
 initializations from 'sequencing.dat'
  DUR REL DUE
 end-initializations

! One job per position
  forall(k in JOBS) OneJobPos(k):= sum(j in JOBS) rank(j,k) = 1

! One position per job 
  forall(j in JOBS) OnePosJob(j):= sum(k in JOBS) rank(j,k) = 1

! Sequence of jobs
  forall(k in 1..NJ-1)
   Prec(k):= start(k+1) >= start(k) + sum(j in JOBS) DUR(j)*rank(j,k)

! Start times
  forall(k in JOBS) Start(k):= start(k) >= sum(j in JOBS) REL(j)*rank(j,k)

! Completion times
  forall(k in JOBS) 
   Complete(k):= comp(k) = start(k) + sum(j in JOBS) DUR(j)*rank(j,k)

! Lateness
 forall(k in JOBS) 
  Late(k):= late(k) >= comp(k) - sum(j in JOBS) DUE(j)*rank(j,k) 

 forall(j,k in JOBS) rank(j,k) is_binary 

 YFACT:=3
 svgsetgraphviewbox(0,0,max(j in JOBS)DUE(j)+10, 12*YFACT)
 svgsetgraphscale(10)

! Objective function 1: minimize latest completion time
 forall(k in JOBS) Finish(k):= finish >= comp(k)
 minimize(finish)
 print_sol(1)
 draw_sol(1)

! Objective function 2: minimize average completion time
 minimize(sum(k in JOBS) comp(k))
 print_sol(2)
 draw_sol(2)

! Objective function 3: minimize total tardiness
 minimize(sum(k in JOBS) late(k))
 print_sol(3)
 draw_sol(3)

 svgwaitclose("Close browser window to terminate model execution.", 1)

!-----------------------------------------------------------------

! Solution printing
 procedure print_sol(obj:integer)
  writeln("Objective ", obj, ": ", getobjval,
          if(obj>1, "  completion time: " + getsol(finish), "") ,
          if(obj<>2, "  average: " + getsol(sum(k in JOBS) comp(k)), ""),
          if(obj<>3, "  lateness: " + getsol(sum(k in JOBS) late(k)), ""))
  write(strfmt("",6))
  forall(k in JOBS) write(strfmt(getsol(sum(j in JOBS) j*rank(j,k)),4))
  write("\n",strfmt("Rel",-6))
  forall(k in JOBS) write(strfmt(getsol(sum(j in JOBS) REL(j)*rank(j,k)),4))
  write("\n",strfmt("Dur",-6))
  forall(k in JOBS) write(strfmt(getsol(sum(j in JOBS) DUR(j)*rank(j,k)),4))
  write("\n",strfmt("Start",-6))
  forall(k in JOBS) write(strfmt(getsol(start(k)),4))
  write("\n",strfmt("End",-6))
  forall(k in JOBS) write(strfmt(getsol(comp(k)),4))
  write("\n",strfmt("Due",-6))
  forall(k in JOBS) write(strfmt(getsol(sum(j in JOBS) DUE(j)*rank(j,k)),4))
  if(obj=3) then
   write("\n",strfmt("Late",-6))
   forall(k in JOBS) write(strfmt(getsol(late(k)),4))
  end-if
  writeln
 end-procedure

!-----------------------------------------------------------------

! Solution drawing
 procedure draw_sol(obj:integer)
   if obj>1 and svgclosing then exit(0); end-if
!   svgerase("msg")

   if obj=1 then svgaddgroup("msg", "Objective", SVG_BLACK); end-if
   svgaddtext("msg",0,YFACT*3*obj-1,formattext("Objective %d: %g %s%s%s", obj, getobjval,
          if(obj>1, "  completion time: " + getsol(finish), ""),
          if(obj<>2, "  average: " + getsol(sum(k in JOBS) comp(k)), ""),
          if(obj<>3, "  lateness: " + getsol(sum(k in JOBS) late(k)), "")))
   forall(j in JOBS) do
     pos:=round(getsol(sum(k in JOBS) k*rank(j,k)))
     if obj=1 then 
       svgaddgroup("J"+j, "Job "+j)
       svgsetstyle(SVG_FILL,SVG_CURRENT)
     end-if
     svgaddrectangle("J"+j, start(pos).sol,YFACT*3*obj,comp(pos).sol-start(pos).sol, YFACT)
   end-do

   svgrefresh
   if obj<3 then svgpause; end-if
 end-procedure

end-model 
 

© 2001-2026 Fair Isaac Corporation. All rights reserved. This documentation is the property of Fair Isaac Corporation (“FICO”). Receipt or possession of this documentation does not convey rights to disclose, reproduce, make derivative works, use, or allow others to use it except solely for internal evaluation purposes to determine whether to purchase a license to the software described in this documentation, or as otherwise set forth in a written software license agreement between you and FICO (or a FICO affiliate). Use of this documentation and the software described in it must conform strictly to the foregoing permitted uses, and no other use is permitted.